25 October 2007

Notes from The Prez



An email from Don Somers, detailing progress:


Note new window glass on second level windows. Down spouts now installed. The door with primer has just been restored. More trim painting completed. After today's project meeting, the expectation is to be completed on the exterior by the end of next week. Only door hardware, replacement of the access door to the second floor and interior window priming will remain, and may not be done for a while yet.


Next week will see the water line and storm drain system installed, the parking area will be sculpted and graveled, and concrete poured for the westside platform.


Don